Progress since previous newsletter
Scaffolding completed
Just before Christmas the scaffold and netting were completed on schedule across all four blocks, these structures are all monitored daily and inspected weekly by certified inspectors. Please remember that your balconies are currently locked and must not be accessed and please do not climb on the scaffolding structure.
Fire Alarms Systems
In December last year the installation of the fire alarm system across Charlton House, Haviland House, John Cozens House, and Langton House was complete. To date, all feedback from the new installations has been positive, however there were two activations in January that were reported as false alarms.
We are in the process of carrying out a full investigation to establish the cause of these activations. Please note that the alarms are equipped with addressable panels, enabling us to identify and trace any issue to the specific device and individual flat concerned. If you experience any alarm-related issues, please email stjudes@bristol.gov.uk.
Structural Survey
Structural and fire safety surveys began in December last year. We expect to receive these final surveys by the end February 2026.
Sprinkler installation
The project team is currently in the process of obtaining detailed quotations for the sprinkler installations across Charlton House, Haviland House, John Cozens House and Langton House. Once this stage is complete, the next step will be to initiate the Building Safety Regulator application in conjunction with the appointed contractor. This will enable the development of the design, associated documentation, and all statutory requirements necessary for approval.
|